Case Study : Forging Plant Design And Installation Support

Client : Forging Industry In Asia
Requirement :
  • Design, Analyze And Optimize Existing Facility
  • Consulting For Automation Concepts
  • Vendor Development And Installation Support
Duration : 10 Months
Efforts : 17 Man-Months

Benefits To Customer
  • Improved Throughout (190 To 130 Parts/Shift)
  • Manpower Reduction From 8 Per Shift To 3 Per Shift By Adding New Automation Concept
  • Overall Productivity Improvement With Optimized Layout And Automation Concept
  • Installation Time Reduced By 1.5 Months (Planned 5Months, Reduced To 3.5 Months )